A newly build industrial complex (2021), with a total of 9000m2, has suffered differential subsidence creating cracks on the floor and building walls, also affecting industrial substructures and equipment. The existing foundation reinforcement had to be done using a system that could work inside the complex without affecting much its industrial operation.
The selection of ARCOS micropiles was made as simple and effective method, that could be implement in tight spaces. The rig could access all the identified subsiding areas (indoor or outdoor) and without the need of moving or dismantling existing structures/equipment. ARCOS was responsible to install the shaft-grouted micropiles.
The installation of the ARCOS shaft-grouted steel micropiles involves the injection of cement grout that will fill up the inner and outer (annulus) space of the pile, that provides improved skin friction to the element.
Challenges
Operating industrial complex with installed equipment and tight areas, besides the low head room. The areas that have been intervened were all having space limitations. It was also important to keep the operation as clean as possible and causing minimal disruption to the factory operation.
Pile installation required the mobilization and demobilization for different areas in the complex (indoors & outdoors) and having the most various uses.



Solution
ARCOS Shaft-grouted steel micropiles have been installed to consolidate the exiting foundation, stopping subsidence and offering better bearing capacity to the industrial equipment. ARCOS micropiles are cost effective and can be installed in any type of environment and space restrictions.
The pile driving rig is lightweight and could be easily mobilized and demobilized to the various locations. It could also be configured and oriented according to the available space. Being possible to assemble the rig’s support legs on top of existing industrial equipment and with different individual lengths.
Pile steel pipe is drive dry, to the design depth or by achieving refusal criteria. After it will be injected using cement grout, mixed on site.
Key Figures
Scope:
A total of 507 driven and grouted ARCOS piles with steel pipe and Ø15cm, reaching up an average 27m in depth: 12620.71m total length.
Achievements:
Daily production between 100m to 150m per day. All pile project completed from 9th august 2022 to 23rd march 2023. Two static load tests were performed to prove pile bearing capacity of 40Tf.
Geology:
The site soil profile is basically composed by silty sand, and a base of compact silty Sand (NSPT 48-60) at an average depth of 28m.